Which differences matter?
Illustrative example. A quoted transformer without a specified test is not directly comparable with one that includes the test.
| Field | Purpose |
|---|---|
| Quote reference | Find the condition |
| Affected requirement | Show the RFQ link |
| Consequence | Explain the comparison gap |
| Disposition | Record the buyer decision |
What is the evaluation principle?
The cited FAR provisions govern specified US federal simplified acquisitions, not ordinary private engineering tenders. They are an example of disclosing the evaluation basis and evaluating against the solicitation.
Sources: Acquisition.gov: FAR 13.106-2, Evaluation of quotations or offers
Common questions
What else should the bid team know?
Is a qualification an automatic rejection?
No. The buyer applies its approved evaluation rules.
Can it be silently priced in?
No. Keep any adjustment visible and approved.