What should the working table show?

Illustrative example. Replace the prompts with approved package information and the buyer's evaluation rules.

RFQ working matrix
TopicRequired contentControl
ScopeIncluded equipment and interfacesDeviation record
TestingFactory and site evidenceTest schedule
DocumentsDrawings, manuals and dataSubmittal register
CommercialCurrency, validity and optionsComparison sheet

What does the source support?

FAR 13.106-2 states that quotations are evaluated on the basis established in the solicitation for applicable federal procurements. Private buyers should define their own approved basis.

Sources: Acquisition.gov: FAR 13.106-2, Evaluation of quotations or offers

What should remain open?

Record unanswered supplier questions, qualifications and missing evidence in a clarification or evaluation log. The responsible engineering and commercial leads approve the final position.

Common questions

What else should the bid team know?

Does this guide select a supplier?

No. It structures evidence for the buyer's approved evaluation process.

Can a blank response be treated as included?

No. Mark it open and request clarification.

Who approves technical compliance?

The responsible project engineer reviews technical compliance and performs any engineering sign-off.

Primary sources

  1. FAR 13.106, Soliciting competition, evaluation of quotations, and awardAcquisition.gov
  2. FAR 13.106-2, Evaluation of quotations or offersAcquisition.gov
  3. Request for QuotationsUS General Services Administration