What does a calendar calculation tool establish?

Microsoft documents WORKDAY.INTL as calculating dates using a specified number of workdays, custom weekends and optional holidays. Those settings explain why an explicit calendar matters. The function does not decide which days the supplier actually works or what the contract means.

RFQ Templates is independent and is not affiliated with Microsoft. Obtain the actual supplier and contractual basis before calculating an equipment milestone. This article is not legal advice and does not turn a software default into an agreed commercial term.

Sources: Microsoft: Microsoft Support: WORKDAY.INTL function

Which RFQ fields make lead times comparable?

Separate duration from its trigger and endpoint. Dispatch, delivery, document approval and completion can be different milestones even when the same number of days is quoted.

Which RFQ fields make lead times comparable?
Calendar fieldClarification to requestComparison control
DurationCalendar days or specified working daysKeep the original quoted unit
TriggerActual agreed event and evidenceDo not start from an assumed email date
Counting ruleWhether the trigger day is includedRecord the first counted day
Working weekSupplier-specific working and closed daysDo not assume Saturday and Sunday
ExceptionsAgreed holidays or shutdown exclusionsRetain the actual calendar reference
EndpointDispatch, arrival or other milestoneDo not compare unlike endpoints

What difference can a weekend make?

Illustrative example. A fictional quote starts counting after a Friday trigger called day 0. Six calendar days finish on Thursday, day 6. With only Monday to Friday treated as working days, no holidays and the same excluded trigger day, six working days finish on the following Monday, day 10.

The example supplies its assumptions expressly. It is not an actual promised delivery date or a rule for all countries and factories. A different weekend, holiday, shutdown or inclusive-start convention changes the result. Transit duration and unloading remain separate unless the actual quote includes them.

How should the comparison be approved?

Keep the quoted wording, agreed clarifications and calculation assumptions with each supplier row. Refer uncertainty to the designated commercial contact rather than silently normalizing every response to a default five-day week.

Recheck the milestone after an authorized trigger or calendar change. Preserve the prior forecast and the reason for the revision; do not rewrite it as an unchanged supplier commitment.

Common questions

What else should the bid team know?

Does days always mean calendar days?

No. Obtain the actual agreed definition.

Does Excel know the supplier's shutdown dates automatically?

No. Use the verified calendar and required inputs.

Is a dispatch date the same as delivery?

Not necessarily. Keep the quoted endpoint explicit.